Construction ramping up on roads around Foxconn site in Racine County

MILWAUKEE -- Construction is ramping up on the roads around the Foxconn site in southern Racine County -- which is east of I-94 between County KR and WIS 20. Jason Roselle with the Wisconsin Department of Transportation joins FOX6 WakeUp to talk about everything that's going to impact your commute.

2018/2019 Continuing Construction Efforts in 2019

International Drive: Began August 2018/Completion Fall 2019

  • New four lane concrete roadway connecting WIS 11 to WIS 20

Braun Road (Phase 1): Began August 2018/Completion Fall 2019

  • Reconstruct to six lane concrete roadway between East Frontage Road and County H

2019 Construction

County KR (Phase 1 of 2): Spring 2019/Completion Late 2019

  • Reconstruct to six lane concrete roadway between East Frontage Road and County H

County H (Phase 1 of 2): Spring 2019/Completion Late 2019

  • Reconstruct to four lane concrete roadway connecting Braun Road and County KR

Wisconn Valley Way: Spring 2019/Completion Late 2019

  • New four lane concrete roadway connecting WIS 11 and County KR

WIS 11 (Phase 1 of 2): Begins Summer 2019/Completion 2019

  • Widening of WIS 11 to the south

Braun Road (Phase 2): Summer 2019/Completion Late 2020

  • Reconstruct to four lane concrete roadway between County H and Willow Road


from FOX6Now.com https://ift.tt/2NF6KC0
via Fox6now

Labels: FOX6Now.com, IFTTT

Anda baru saja membaca artikel Construction ramping up on roads around Foxconn site in Racine County. Silakan share artikel ini ke media sosial anda.

Bagikan:

0 Komentar untuk "Construction ramping up on roads around Foxconn site in Racine County"

Slot Iklan Google AdSense